Construction of new high-voltage 110kV for Deutsche Bahn on behalf of LTB Leitungsbau GmbH from 10.10.2011 to 15.12.2011
Work on this project involved two assembly brigades, very busy schedule and have set 24 towers. Half of them were located in the forest, which limited the construction site and made crane access difficult. In forest towers were up to 60 meters, which in the 110kV lines are rarely seen.