380 kV Rheinau Hoheneck (Germany)

Modernization of high-voltage 380 kV line for AMPRION GmbH on behalf of GA Hochspannung Leitungsbau GmbH between 02.08.2010 and 01.10.2010


back
Unicorn

Gallery



Realization of the project

We had to involve three teams of three people. In total, for 4.5 weeks we have replaced over 24 tonnes of angle bars on crossbeams of 33 masts and used pneumatic winch, magnetic drills and other necessary certified equipment. Unicorn as always have maintained all safety regulations and perfect organization of work at site.