Project performed for SVENSKA KRAFTNÄT with cooperation with TECNOSWEDEN (Swedish subsidiary of TECNOLINES).
Project performed for SVENSKA KRAFTNÄT with cooperation with TECNOSWEDEN (Swedish subsidiary of TECNOLINES). The scope of works was : transport, pre-assembling and erection of 300kV power line. We erected over 100 towers with total weight over 1100 ton. Project was conducted in very difficult terrain and weather conditions in period from 05.2013 till 12.2013.